To confirm the Minutes of the meeting held on 23rd July, 2019 (copy attached). Minutes: The Minutes of the meeting of the Cabinet held on 23rd July, 2019 were confirmed and signed by the Chairman. |
|
REVENUE BUDGET MONITORING AND FORECASTING 2019/20 - POSITION AT JULY, 2019 PDF 410 KB To consider Report No. FIN1924 (copy attached), which sets out the Council’s anticipated financial position for 2019/20, based on the monitoring exercise carried out during July, 2019. Presented By: Cllr Paul Taylor, Corporate Services Portfolio Holder Minutes: The Cabinet
considered Report No. FIN1924, which set out the anticipated financial position
for 2019/20, based on the monitoring exercise carried out during July, 2019. Members
were informed that the need for savings or income generation of around
£3,931,000 had been identified for the year. During Quarter 1, net cost
reductions of £3,198,000 had been built into the approved budget, leaving a
budget savings target of £733,000 and an outturn target of £1 million. It was
reported that the projected 2019/20 year-end balance of the General Fund stood
at £2 million, which was at the top of the range set out in the Medium Term
Financial Strategy. It was noted that the Stability and Resilience Fund could
be used to support the General Fund balance, should the predicted reductions in
net expenditure not be achieved. The Cabinet NOTED the latest Revenue
Budget monitoring position, as set out in Report No. FIN1924. |
|
CAPITAL PROGRAMME MONITORING AND FORECASTING 2019/20 - POSITION AT JULY, 2019 PDF 273 KB To consider Report No. FIN1925 (copy attached), which sets out the Council’s position regarding the Capital Programme for 2019/20, based on the monitoring exercise carried out during July, 2019. Presented By: Cllr Paul Taylor, Corporate Services Portfolio Holder Minutes: The Cabinet
received Report No. FIN1925, which provided the latest forecast regarding the
Council’s Capital Programme for 2019/20, based on the monitoring exercise
carried out during June, 2019. The Report advised that the Capital Programme
for 2019/20, allowing for slippages from the previous financial year and
additional approvals, totalled £72,381,000. It was noted that projects of major
financial significance to the Council in the Capital Programme for 2019/20
included the Aldershot Town Centre Integration and Union Street developments, the
Farnborough Civic Quarter development, the finalisation of a loan to
Farnborough International and the further acquisition of investment properties.
The Report set out a request for additional approvals to facilitate capital
projects within 2019/20 in respect of the Games Hub, Aldershot, the
implementation of Office 365 for the Council and the Blunden Road Recreation
Ground, Farnborough. The Cabinet RESOLVED that (i)
The latest Capital
Programme monitoring position, as set out in Report No. FIN1925, be noted; and (ii)
the additional capital requests for 2019/20, as set
out in the Report, be approved. |
|
REGENERATING RUSHMOOR 2019/20 - QUARTER 1 PROGRESS REPORT PDF 378 KB To receive Report No. RP1914 (copy attached), which sets out a progress report for the ‘Regenerating Rushmoor’ programme for the first quarter of 2019/20. Presented By: Cllr Martin Tennant, Major Projects and Property Portfolio Holder Minutes: The Cabinet received
Report No. RP1914, which set out progress towards the Council’s Regenerating Rushmoor
Programme for the first quarter of 2019/20. In particular, the Report
highlighted the current position in relation to the Galleries and High Street
Multi-storey Car Park, Aldershot, the Farnborough Civic Quarter and the project
to provide a new access road at Invincible Road, Farnborough. The Cabinet NOTED the progress made towards delivering the
Regenerating Rushmoor Programme, as set out in Report No. RP1914. |
|
MOOR ROAD RECREATION GROUND - NEW FACILITIES PDF 400 KB To consider Report No. DSP1908 (copy attached), which sets out a proposal for the installation of new facilities at Moor Road Recreation Ground, Farnborough. Presented By: Cllr Adrian Newell, Democracy, Strategy and Partnerships Portfolio Holder / Cllr Maurice Sheehan, Operational Services Portfolio Holder Minutes: The Cabinet considered Report No. DSP1908, which set out a proposal to
provide new facilities at Moor Road Recreation Ground, Farnborough. The Operational Services Portfolio Holder introduced the Report and it
was noted that the Development Management Committee had given planning
permission at its meeting on 14th August, 2019, subject to conditions. Members
heard that the proposed new facilities would be likely to encourage more people
to enjoy open spaces and become active. The project would be mainly funded from
Section 106 developers contributions but successful funding awards had also
been received from Sport England and Prospect Estate Big Local (PEBL). It was also requested that £20,000 should be
drawn down from the Car Park Enhancements Earmarked Reserve and the sum of
£1,020 should be included in future budgets to allow for the inspection costs
of the facilities. The Cabinet welcomed the proposal and, in response to a question, it was
confirmed that the installation of CCTV at the site would be considered as part
of a wider review of CCTV provision in the Borough. The Cabinet RESOLVED that (i)
the
provision of new facilities at the Moor Road Recreation Ground be approved, in
accordance with the proposals set out in Report No. DSP1908 and the Head of
Democracy, Strategy and Partnerships be authorised to proceed with the delivery
of the project; and (ii)
the drawdown of £20,000 from the Car Park
Enhancements Earmarked Reserve and the inclusion of annual inspection costs of
the facilities of £1,020 per annum from 202/21 onwards, as set out in the
Report, be approved. |
|
EXCLUSION OF THE PUBLIC To consider resolving: That, subject to the public interest test, the public be excluded from this meeting during the discussion of the undermentioned items to avoid the disclosure of exempt information within the paragraphs of Schedule 12A to the Local Government Act, 1972 indicated against such items: Item Schedule Category Nos. 12A Para. No. 7, 8 and 9 3 Information
relating to financial or business affairs Minutes: RESOLVED: That, taking into account the public interest test, the public be
excluded from the meeting during the discussion of the under mentioned items to
avoid the disclosure of exempt information within the paragraph of Schedule 12A
to the Local Government Act, 1972 indicated against the items: Minute Schedule Category Nos. 12A Para. No. 34, 35 and 3 Information relating to
financial or business affairs 36 |
|
THE FOLLOWING ITEMS WERE CONSIDERED |
|
APPLICATION FOR SECTION 49 REMISSION OF NON-DOMESTIC RATES To consider Exempt Report No. FIN1926 (copy attached), which gives details of an application for the remission of non-domestic rates due to hardship. Presented By: Cllr Paul Taylor, Corporate Services Portfolio Holder Minutes: The Cabinet considered Exempt Report No. FIN1926, which set out an application for the remission of non-domestic rates on the grounds of hardship. Members assessed the application from Wimpey (Aldershot) Limited, Nos. 29 – 31 Wellington Centre, Aldershot, taking into account the evidence of financial hardship supplied and whether it was in the interests of local taxpayers to subsidise the business. The Cabinet took into account the nature and circumstances of the business and the availability of alternative facilities in the area. The Corporate Services Portfolio Holder and the Council’s Principal Revenues and Benefits Officer were due to meet with the proprietor at the premises to discuss the application in detail on 21st August, 2019. In response to a question, it was agreed that, in future, applicants for hardship relief would be encouraged to seek a rent reduction at the same time, if applicable. The Cabinet RESOLVED that, subject to the outcome of the Corporate Services Portfolio Holder’s visit to the premises on 21st August, 2019, 50% hardship relief be granted to Wimpey (Aldershot) Limited for the period from 1st April, 2019 to 31st March, 2020. |
|
ALDERSHOT REGENERATION - SITE ASSEMBLY To consider Exempt Report No. RP1918 (copy attached), which sets out a proposal for the acquisition of a property as part of the Aldershot town centre regeneration proposals. Presented By: Cllr Martin Tennant, Major Projects and Property Portfolio Holder Minutes: The Cabinet considered Exempt Report No. RP1918, which set out a
proposal for the acquisition of a site that formed part of the Council’s
Aldershot town centre regeneration proposals. The Report set out details of the proposed acquisition. Authority to
acquire the site had been granted previously by the Cabinet but this Report set
out additional associated holding costs that had been identified as part of the
due diligence process. It was felt that this site was integral to the
regeneration proposals for Aldershot town centre, which would be taken forward
by the Rushmoor Development Partnership. The Cabinet RESOLVED that (i)
the
acquisition of the freehold associated with the site identified in paragraph 1.1
of Exempt Report No. RP1918, at the value identified in paragraph 3.5, be
approved; and (ii)
the Executive Head of Finance be authorised to enact
the financial arrangements outlined in paragraph 4.5 of the Report. |
|
SURRENDER OF LEASE - UNION STREET, ALDERSHOT To consider Exempt Report No. RP1915 (copy attached), which sets out a proposal for the surrender of the lease in respect of a property owned by the Council and forming part of the Aldershot town centre regeneration site. Presented By: Cllr Martin Tennant, Major Projects and Property Portfolio Holder Minutes: The Cabinet considered Exempt Report No. RP1915, which set out a
proposal for the surrender of a lease for a premises
of which the Council was the freeholder. It was considered that the site was
integral to the Council’s regeneration proposals for Aldershot town centre. The Council had been negotiating with the leaseholder for the previous
six months and had now reached a provisional agreement for the surrender on the
terms that were set out in the Report. It was also proposed to provide a budget
for specific costs that were likely to be incurred once vacant possession had
been secured. In discussing this matter, the Cabinet expressed support for the
proposed approach and considered this to be a key step in the overall proposals
for the town centre regeneration. The Cabinet RESOLVED that (i)
the
acceptance of the lease offer from the leaseholder, as set out in paragraph 3.3
of Exempt Report No. RP1915, be approved; (ii)
the ringfencing of the
final quarter rental income apportionment opportunity of £50,000, to cover
revenue implications (holding costs) for the period prior to the property being
redeveloped by the Rushmoor Development Partnership, as set out in the Report,
be approved, with actual expenditure and variances thereof to be reported
through budget monitoring; (iii)
the Executive Head of Regeneration and Property, in
consultation with the Major Projects and Property Portfolio Holder, be
authorised to agree the final terms of the surrender offer; and (iv)
the Executive Head of Finance be authorised to
utilise the monies to be received in respect of the lease surrender, which
might include, but not be limited to, using the monies as a revenue contribution
to capital outlay. |